Preparing the BT 3002 cable from BTS to DDF block with T 43 sockets at BTS end and T 43 Plug at DDF end.
Preparing the BT 3002 cable from DDF to M/W equipment with T 43 Plug at DDF end and BNC Male Connector at M/W equipment.
Pix Alarm wiring to be done with termination of alarm points on the krone DDF.
Termination & Testing of all external alarms on the Krone DDF.
NMS Cable termination as per requirement.
VSWR test of antennas using site master test equipment.
Frequency calibrations through freq counter equipment.
Cross connection through Far end at bypassing.
Power Calibration & Power measurement through Digital Power Meter.
Call & Sector swapping testing using Net Monitor Software by cell phone.
| Documents |
|
|
|
BTS & M/W inventory list with product serial numbers.
Final Site Layout drawing & plan
Site inventory list with all equipment serial numbers
|
|